logo search
182-методичка-асп

Text 1: Portland Cement Production

http://www.cement.org/basics

Two different processes, "dry" and "wet," are used in the manufacture of portland cement.

When rock is the principal raw material, the first step after quarrying in both processes is the primary crushing. Mountains of rock are fed through crushers capable of handling pieces as large as an oil drum. The first crushing reduces the rock to a maximum size of about 6 inches. The rock then goes to secondary crushers or hammer mills for reduction to about 3 inches or smaller.

In the wet process, the raw materials, properly proportioned, are then ground with water, thoroughly mixed and fed into the kiln in the form of a "slurry" (containing enough water to make it fluid). In the dry process, raw materials are ground, mixed, and fed to the kiln in a dry state. In other respects, the two processes are essentially alike.

The raw material is heated to about 2,700 degrees F in huge cylindrical steel rotary kilns. Kilns are frequently as much as 12 feet in diameter ­ large enough to accommodate an automobile and longer in many instances than the height of a 40-story building. Kilns are mounted with the axis inclined slightly from the horizontal. As the material moves through the kiln, certain elements are driven off in the form of gases. The remaining elements unite to form a new substance with new physical and chemical characteristics. The new substance, called clinker, is formed in pieces about the size of marbles.

Clinker is discharged red-hot from the lower end of the kiln and generally is brought down to handling temperature in various types of coolers. The heated air from the coolers is returned to the kilns, a process that saves fuel and increases burning efficiency.